The crushing equipment adopts hammer double-rotor impact crusher and the product structure is developing for the fine crushing. The development of high-new equipment requires plentiful functional materials and the application of modern fine crushing technology has become an important symbol of embodying the national technology level.
The working process of the ball mill anchor bolt deviation is easily happened the situation that is different from the foundation drawing,this makes some deviation between the anchor bolt and the foundation,this deviation is the common phennomenon,this phennomenon in ball mill industrial called anchor bolt accident,if you happen this thing, do not worry,following the below 3 point can totally solve the problem.
1.Ball mill anchor bolt level deviation handling
If the standard height of the foundation more higher,then can sut some and use the tap to work out a thread.If the standard height is so low (deviation is less than 15 mm).The usual way is use the Oxyacetylene flame to make the bolt heated into red and elongation,both the two side of the diamter,it should be burn-on 2 rebar.If the standard height of the foundation bolt is lower,and the deviation is more than 15mm,then can not be heated methods,then we can cut off the foundation bolt and welding a new system screw the Chinese juniper,At the same time in the butt welding repair welding in four The root of the reinforcing steel bar. Level after the treatment, and should also complement placing of concrete. To a service-oriented brand integrity,As the professional manufacturer of complete sets of mining machinery, like sand washer, Henan Hongxing is always doing the best in products and service.rock crushers:http://www.crusher-machine.com/1.html
2.Ball mill anchor bolt live drawing processing
When screw down the nut for the foundation bolt,Because overexert, use hammer wrenches, or because the installation is bad and cause shock Strike, vibration and other reasons,Anchor bolt from secondary water reserve the hole drawn out, this phenomenon is called "live drawing" .The way to processing the accident,put anchor bolt lumbar coagulation chisel,And in the screw on welding two root U The steel bar, and then fill poured concrete, so that he may live drawn anchor screw inspection retighten prison.If because Lubricating oil etching secondary water layer joint surface cause of live dial the, the case shall then be partial foundation broken, new embedded anchor Bolt.
The unification of the installation, commissioning, maintenance and other aspects of technical standards become as the important measure towards lean service. The technical service center on the basis of the technical standards provides customers with a uniform, traceable, testable service, which not only provides more protection for the stable operation of the production line, but also further shortens the response time and service time. The optimal program design, standardized on-site installation, commissioning and fine operation, maintenance, training, timely troubleshooting help Henan Hongxing Mining Machinery service centers continue to product advantages to help more customers to reduce production costs and grasp the opportunities in the market.